ADU Garage Conversion

Trenching for water, sewer, electrical, and gas supply.

Trenching for phase 1: ABC underpinning foundation.


Install ABS sewer drain, copper water line, gas line, and electrical.

Install forms + rebar for phase 1: ABC underpinning foundation


Install concrete for for phase 1 + 2: ABC underpinning foundation.

Foundation complete. Framing started.


Rough plumbing & electrical complete. Rough framing & Mechanical complete.


78" shower with custom frameless hinged door & raised toilet seat with 2 drawer vanity.

LVP Waterproof flooring & shaker cabinets with bar pulls.